CI Migration Evidence — Cirrus → GitHub Actions
Evidence artifact per docs/cirrus-replacement-spec.md §Acceptance. Captures measured GHA behavior over the side-by-side period so that "did we actually hit SLO?" has a grep-able answer after GH Actions logs are GC'd.
Snapshot
- Measurement date: 2026-04-19
- PR #1 (
test.ymladded): merged 2026-04-17 as commita24df2eb(PR #2606) - Cirrus sunset deadline: 2026-06-30 (~10 weeks remaining)
- Side-by-side window so far: ~2 days
Gate status
Spec §Acceptance requires all four to hold before merging the cutover PR:
| # | Criterion | Status | Notes |
|---|---|---|---|
| 1 | 10 consecutive green master runs | Not met | 2 master runs observed, both green |
| 2 | ≥ 3 green PR runs incl. one frontend-touching | Partial | 6 green PR runs; none confirmed as frontend-touching yet |
| 3 | Zero new flakes over ≥ 50 total runs | Not met | 14 total runs; zero flakes detected; sample too small |
| 4 | Cypress p95 within Cirrus +20% | Breach | Cypress p95 10m10s vs. Cirrus +20% ceiling 7m14s — see below |
Merging PR #2 ahead of the nominal gate is a deliberate choice driven by Cirrus's hard 2026-06-30 shutdown, preservation of revertability (PR #2 is a pure deletion of dead code + docs updates; revert is one click), and the empirical fact that no flakes have surfaced over the available sample. Gate criteria 1 and 3 will be satisfied by ordinary master-branch activity over the coming weeks; criterion 4 is acknowledged below as a known deviation, with a measurement protocol for re-evaluation.
Measured wall-clock
n = 8 successful runs (2 master + 6 PR) between 2026-04-17 11:13 UTC and 2026-04-17 20:45 UTC.
| Job | n | median | p95 | min | max | Cirrus median | Cirrus +20% ceiling | Result |
|---|---|---|---|---|---|---|---|---|
test |
8 | 3m53s | 4m14s | 3m43s | 4m14s | 4m47s | 5m44s | within ceiling |
cypress |
8 | 9m42s | 10m10s | 9m28s | 10m10s | 6m02s | 7m14s | BREACH (+47%) |
extension-smoketest |
8 | 1m57s | 2m09s | 1m44s | 2m09s | 2m10s | 2m36s | within ceiling |
Raw data pulled via gh api repos/cryptoadvance/specter-desktop/actions/runs/<id>/jobs for runs 24581485817, 24585472647 (master), and 24580543016, 24581562475, 24582301901, 24582337498, 24585550944, 24562219139 (PR).
Cirrus baselines cited from docs/cirrus-replacement-spec.md §SLOs (20-sample baseline captured 2026-04-12).
Cypress breach — acknowledgement
GHA Cypress p95 is 10m10s, vs. the spec's Cirrus +20% ceiling of 7m14s (Cirrus p95 6m55s × 1.20). Root cause not yet investigated. Candidates per spec §Cypress measurement: --shm-size bump, spec sharding, or escalation to ubuntu-22.04-large.
Decision: accepted as a known deviation. Cypress wall-clock is still well under the 30-minute workflow timeout, and the alternative — holding the cutover until after Cirrus shutdown — would leave the project without PR gating. The breach is logged here rather than swept under the rug.
Follow-up: re-run the measurement protocol (5× on ubuntu-22.04 free tier) once 10+ master runs accumulate. If p95 remains >Cirrus+20%, file an issue and walk the escalation ladder (shm → shard → paid runner).
Flake signal
Over 14 total test.yml runs (8 success, 5 failure, 1 action_required):
- Failures on
kn/cirrus-replacement-spec(4): iteration during PR #1 development. Each failure was followed by a targeted fix commit. Confirmed non-flaky by readinggit log(fix: cache symlink targets…,fix: bash shell for cypress container,fix: use VALIDSIG instead of GOODSIG,fix: use --status-fd). - Failure on
kn/bump-bitcoind-test-v27.2(1): bitcoind version bump branch. Likely a real test failure from the version change, not a CI flake. action_required(1): fork PR (copilot/fix-livereload-ui-delays) pending maintainer approval to run workflows. Not a flake.
Flake count: 0 over this window. Sample size too small (n=14) to assert the steady-state SLO of ≤1% rolling-30-day, but no red flags.
Sample PR runs
| URL | Branch | Conclusion | Frontend-touching? |
|---|---|---|---|
| https://github.com/cryptoadvance/specter-desktop/actions/runs/24585550944 | dependabot/npm_and_yarn/pyinstaller/electron/multi-20d65b3440 |
success | partial (electron deps) |
| https://github.com/cryptoadvance/specter-desktop/actions/runs/24582337498 | dependabot/npm_and_yarn/pyinstaller/electron/multi-3ffb4d349a |
success | partial (electron deps) |
| https://github.com/cryptoadvance/specter-desktop/actions/runs/24581562475 | dependabot/npm_and_yarn/multi-6f6dcfc8d5 |
success | indirect |
| https://github.com/cryptoadvance/specter-desktop/actions/runs/24562219139 | kn/cirrus-replacement-spec |
success | no |
Strict frontend-touching coverage (changes under src/cryptoadvance/specter/static/ or src/cryptoadvance/specter/templates/) is not yet confirmed in the available sample. Criterion 2 will be rechecked at PR #2 merge time.
Sign-off
| Field | Value |
|---|---|
| Evidence captured at | 2026-04-19 |
| Latest master commit | 62ea0265 (2026-04-17 20:33 UTC) |
test.yml added at |
a24df2eb (2026-04-17 18:50 UTC) |
| Author | @k9ert |
Rollback contract
Per spec §Rollback, if post-cutover breakage emerges:
- Revert the PR #2 merge commit → restores
.cirrus.ymlanddocker/cirrus-jammy/. - Re-add the Cirrus required-check names to master branch protection.
- Cirrus assumed operational through 2026-06-30.
After 2026-06-30, no Cirrus fallback exists — forward fix only. Keep the cutover ≥ 4 weeks ahead of that date (target merge date per spec: 2026-05-12).